Russell Union HVAC Upgrade

Project Overview: 

Estimated Construction:

5/7/2017 – 8/7/2017

Project Manager:

Sandra Wilkinson

swilkinson@georgiasouthern.edu

The Russell Union HVAC upgrades will replace all of the Air Handling Units, VAV boxes, and Fan Coil Units. This project is going to improve the air flow and quality. Please see the link for the temporary locations of the  Russell Union offices.

Targeted Timeline:

Construction Begins: 5/7/2017

Construction Ends: 8/7/2017

Building Opens: 8/7/2017

*Dates are subject to change. Please contact the Project Manager with any questions.

Last updated: 7/14/2017

Facilities Planning, Design & Construction • PO Box 8012 Statesboro, GA 30460 • (912) 478-5752